Southeast Drainage Project
Project Name
Southeast Drainage Project

Project Description
The project would include a replacement/rehabilitation of a 54 inch storm water conveyance pipe that is responsible for draining a large percentage of Abilene's surface area to the Smoky Hill River. 

Project Budget and Funding
Project costs is estimated between $1 million and $5 million dollars.  The project is to be funded from the storm water fee revenue. 

Construction Year
Tentatively 2015/2016

Current Phase
Planning

Project Engineer
Not Yet Determined.

General Contractor
Not Yet Determined.

Tentative Schedule (subject to change)
Selection of a Consultant:  March-May
Storm water Study:  May-October
Preliminary Engineering: October-March
Construction:  March-September 

Project Updates


Trolley Along
FacebookTwitterRSS
With Abilene
City of Abilene
P.O. Box 519
Abilene, Kansas 67410
Phone: 785-263-2550
Fax: 785-263-2532
1st Combined Arms Battalion
63rd Armor Regiment